Our team of six managed to complete three precast bridges under a very demanding schedule for BNSF Railway -one of North America’s leading freight transportation companies, with a rail network of 32,500 route miles. Notably, the knowledge of our onsite Structure Superintendent and Foreman ensured that this project ran smoothly and safely from start to finish as construction was happening next to a live Railroad Line.
Railway Construction – Clarksville, Missouri
Midwest Heavy Highway Construction Experts.
NAME OF PROJECT
Burns and Gibbs Track Siding Structures
Location of the Project
Clarksville, MO
Project completed for
BNSF
Length of the Project
3 Months
key members
Bill Swallow – Structure Superintendent
Marvin Bautista – Structures Foreman
goals of the project
Complete 3 bridges in 9 weeks
summary of the project
Construct 3 bridges next to a live RR line.
Structures were built from precast concrete shipped from Omaha, NE