Pierce East Levee Bridge
Midwest Heavy Highway Construction Experts.
NAME OF PROJECT
Pierce East Levee Bridge
Location of the Project
Pierce, NE
Project completed for
NDOT
Length of the Project
5 months
key members
N/A
goals of the project
During the winter remove and replace the N-98 bridge over the North Fork River
summary of the project
The bridge construction started in November and continued throughout the winter while the water flows were their lowest. The entire bridge deck was removed and replaced with a steel girder superstructure and cast in place deck. The entire project had to be completed without disturbing any of the levee grades and waterway.