Hwy 42 – James River

Midwest Heavy Highway Construction Experts.

NAME OF PROJECT

Hwy 42 – James River

Location of the Project

Ethan, SD

Project completed for

SDDOT

Length of the Project

1 year

key members

N/A

goals of the project

Remove and replace the HWY 42 bridge over the James River.

summary of the project

During the winter months while the water levels were low the existing bridge was removed and replaced with 2 abutments and 5 piers. Each pier was 45’ tall and constructed in a 35’ deep coffer cell. The pier bents were H-Pile founded with spread footings. This 6 span bridge utilized a Minnesota Type 45 Concrete Girder.